Nexcess Server Configuration Updates (LGW, LHR)

Scheduled Maintenance Report for Server Status | Nexcess

Completed

The scheduled maintenance has been completed.
Posted Jul 28, 2021 - 21:00 EDT

In progress

Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted Jul 28, 2021 - 17:00 EDT

Scheduled

Nexcess system engineers will be updating select core system configurations as part of ongoing maintenance and security hardening measures. These changes will result in reboot to some cloudhosts within each region, resulting in approximately 2-minutes of downtime.

Regression Plan: Should the updates cause issues, engineers will roll back the changes and investigate a root cause.
Posted Jul 27, 2021 - 15:34 EDT
This scheduled maintenance affected: Nexcess Cloud (uk-south-2) and Data Centers & Network (Surrey, UK (LHR), West Sussex, UK (LGW)).